Visible progress. Disciplined execution. A clear route towards commissioning.
Azteca refurbishment is now 77% complete and remains ahead of plan.
Operational readiness continues to be targeted for the end of August 2026, subject to successful commissioning and receipt of the
🚀 Execution momentum at Amapá
Azteca refurbishment is ahead of schedule:
✅ c.48% weighted physical progress
✅ 41% planned progress
✅ Key plant areas advancing
✅ Operational readiness target maintained
Read the full RNS: https://shorturl.at/Uamq0
#KDNC #Amapa #Mining
#KDNC @CadenceMinerals - Azteca Execution Update
✅ Refurbishment works at the Azteca plant, part of the Amapá Iron Ore Project in Brazil, are ahead of the current works schedule
✅ Works programme advancing, with key processing areas close to completion and critical workstreams